1.Installation
First, the pump is placed on the firm cement ground or stone pier. Keep it level. And lock the four pump legs and safety pin. Take the tire off the ground or remove the tier.

Second, make a chute between the outlet of the concrete mixing pump mixer and the hopper of the pump machine, so that the material discharged by the mixer enters the hopper of the pump through the chute. The chute is usually framed by angle steel and welded from 1.5mm thick steel plates. Under the chute with support to make it firm. For the chute, the slope should be appropriate, and the tilt angle should be 25 degrees to 40 degrees. There should be some space between the chute and the pump hopper to clean the hopper and sieve.

Third, usually, the concrete mixing pump should be raised about 20cm. This can increase the volume of the hopper to ensure that the concrete does not flow out (because the forced mixer had better be unloaded at one time so that the concrete flowing into the hopper is more uniform. If discharge time by time, the last concrete are consisted of more stones. It is not good for pumping. If a large capacity mixer is used, a storage hopper can be made beforehand to ensure the continuous material supply.

Fourth, after the concrete mixing pump is installed, we should ensure that the cover door of the pump can be opened and closed freely for easy maintenance and operation.

2.Pipeline Layout
First, the concrete mixing pump pipeline layout should be in the premise of ensuring smooth pumping and normal transmission, as far as possible to shorten its length, and reduce the bending pipe, to reduce the transmission resistance.

Second, it is best to connect the straight pipe above 2m in front of the taper tube before using the elbow tube. We must also ensure that the straight pipe axis and the conical pipe axis overlap.
And do fixed and reliable, so that the cone tube can be quickly installed after disassembly and cleaning.

Third, each pipeline must be firmly connected. A firm fixing device should be added at the bend. A firm point shall be set for every 10m spacing. The pipeline clamp should be suspended so as to dismantle and connect the road. Each clamp must be tightened in place to ensure that the joint is tightly sealed, not leakage slurry, leakage.

Fourth, connect pipeline according to the site construction conditions and the requirements. and arrange the pipelines reasonably to eliminate the hidden dangers.